20.08 Release timeline

Week

Countdown

Specific dates

Milestones

Jun 01 - Jun 05

C-9

libraries + ‘groovy’ meta sync/rebuild - master

Jun 29 - Jul 03

C-5

mid-cycle checkpoint
  • lint/unit/functional tests passing

  • mojo green week (whole team)

  • MOSCI / bundles

Jul 06 - Jul 10

C-4

new charm readiness checkpoint
  • SQA touchpoint: request runs; firm up plans

Jul 20 - Jul 24

C-2

Mon, Jul 20

20.08 libraries freeze
  • libraries sync/rebuild

  • cut stable libraries

  • switch reactive charms to stable libraries

Fri, Jul 24

20.08 charm freeze
  • documentation submitted

Aug 03 - Aug 07

C-0

Wed, Aug 05

20.08 charm release

The weeks and countdown labels are not contiguous because some internal development stages have not been included.