Ocata Review Priorities¶
Here are the Ocata review priorities.
Priority Item |
Owner(s) |
Spec(s) |
---|---|---|
OpenStack “Community” Goal |
||
Community Images |
||
Image Import Refactor |
||
Rolling Upgrades |
Important dates¶
This is an abbreviated list focused on dates relevant to Glance. See Ocata Release Schedule for the complete list for OpenStack.
Milestone |
Week of |
What |
---|---|---|
R-15 |
November 7 |
Glance spec proposal freeze |
R-14 |
November 14 |
O-1 milestone |
R-13 |
November 21 |
Glance spec freeze |
R-10 |
December 12 |
O-2 milestone |
R-9 through R-7 |
December 19 through January 6 |
expect team to be half-strength (at best) due to holidays |
R-5 |
January 16 |
glance_store Ocata release (final release for non-client libraries) |
R-4 |
January 23 |
O-3 milestone, Glance feature freeze, python-glanceclient Ocata release (final release for client libraries) |
R-3 |
January 30 |
RC-1 release and string freeze |
R-1 |
February 13 |
final RCs |
R-0 |
February 20 |
Ocata release |