Ocata Review Priorities

Here are the Ocata review priorities.

Priority Item

Owner(s)

Spec(s)

OpenStack “Community” Goal

Community Images

Image Import Refactor

Rolling Upgrades

Important dates

This is an abbreviated list focused on dates relevant to Glance. See Ocata Release Schedule for the complete list for OpenStack.

Milestone

Week of

What

R-15

November 7

Glance spec proposal freeze

R-14

November 14

O-1 milestone

R-13

November 21

Glance spec freeze

R-10

December 12

O-2 milestone

R-9 through R-7

December 19 through January 6

expect team to be half-strength (at best) due to holidays

R-5

January 16

glance_store Ocata release (final release for non-client libraries)

R-4

January 23

O-3 milestone, Glance feature freeze, python-glanceclient Ocata release (final release for client libraries)

R-3

January 30

RC-1 release and string freeze

R-1

February 13

final RCs

R-0

February 20

Ocata release